Part 2 -
Project Management Theory
Extracts
6.7 Earned Value
Earned Value Analysis (EVA) in its various forms is a widely
accepted method of performance measurement. It is used to estimate how a
project is doing in terms of schedule and budget.
Earned value is
a measure
of the value
of work
performed so far. It uses original estimates
and progress-to-date
to show whether the actual costs
incurred are on budget
and whether the tasks
are ahead of or behind the baseline plan.
It can answer the following questions in time and money:
§
Where
are we now?
§
Where
are we going?
Earned Value Analysis (EVA) involves calculating three key values
for each activity:
1.
Planned
Value
2.
Actual
Cost
3.
Earned
Value
Planned Value
(PV) is the portion of the approved cost
estimate planned to be spent on an activity during a given period.
Actual Cost
(AC) is the total cost incurred in
accomplishing work on the activity during a given period.
Earned Value (EV) is the value of the work actually completed.
Examples:
Planned Value, week 1
§
Task 1: 10 hours at $200 per hour = $2,000
§
Task 2: 20 hours at $200 per hour = $4,000
Results at the end of week 1:
Task 1:
§
Hours worked: 12 => Actual Cost >
(12 X $200) = $2,400
§
Status (percent complete): 100% (Completed):
§
Earned Value % complete X (Total Planned Value)
§
Earned Value = (100% X $2000)) = $2,000
Task 2:
§
Hours worked: 5
=> Actual Cost >
(5 X $200) = $1,000
§
Status (percent complete): 50%:
§
Earned Value % complete X (Total Planned Value)
§
Earned Value = (50% of $4,000) = $2,000
Earned Value Performance Indicators
Cost Variance (CV) = EV – AC
A
positive value is good, while a negative value indicates trouble
Cost Performance Index (CPI) = EV / AC
Cost is under control if 0.95 < CPI <
1.10 (Use
as a guide, not as a hard rule.)
If the CPI is over 1, the project is
progressing at a lower cost than planned.
Schedule Variance (SC) = EV – PV
A positive value is good, while a negative
value indicates trouble
Schedule Performance Index (SPI) =
EV / PV
Schedule is under
control if 0.95 < SPI < 1.10 (Use as a guide, not as a hard rule.)
If the SPI is over 1 the project is progressing
at a faster rate than planned.
Other calculations:
Estimate at Completion (EAC) is a forecast of most likely total project costs
based on project performance and risk quantification.
It can be calculated
in different ways:
EAC = Actual due dates + new estimate for all remaining work
§
Used when past performance shows that the
original estimating assumptions were
fundamentally flawed
EAC = Actual due dates + remaining budget
§
Used when current variances are seen as
typical and the project management team expectations are that similar variances
will not occur in the future
EAC = Actual due dates + remaining budget modified by a performance
factor (CPI)
§
Used when current variances are seen as
typical of future variances
Notes about terminology:
Planned value
is also called Budgeted Cost of Work Scheduled (BCWS).
Actual cost
is also called Actual Cost of Work Performed (ACWP).
Earned value
is also called Budgeted Cost of Work Performed (BCWP).
Earned value must be calculated at the level of cost control and
this might be higher than the level of task control.
Section 11
Project Risk Management
A risk is an uncertain event that, if it occurs, has a positive or negative
effect on a project objective.
A risk trigger is an indication that a risk has occurred or
is about to occur.
11.1 Risk Management
Risk management is the
systematic process of identifying, analyzing and responding to project risk.
§
Risk management minimizes the probability of
adverse events and their consequences for project objectives.
§
Risk management also looks to maximize the
probability and consequences of positive events that may happen to the project.
- The risk management process must ensure that the
level, type and visibility of risk management are commensurate with both
the risk and importance of the project to the organization. (The same risk
will have a different impact on different projects.)
11.2 Risk Management Process
|
|
Risk Management Planning – Decide how to approach and plan the risk
management for the project.
|
|
¯
|
|
Risk Identification – Determine which risks might affect the project
and document their characteristics.
|
|
¯
|
|
Qualitative Risk Analysis – Subjective analysis for occurrence, impact and
criticality.
|
|
¯
|
|
Quantitative Risk Analysis – Numerical analysis for occurrence, impact and
criticality. |
|
¯
|
|
Risk Response Planning – Actions to take about identified risks. |
|
¯
|
|
Risk Monitoring and Control – Keep track of risks and plans, identify new
risks and ensure execution of risk management and response plans. |
|
Risk identification requires an understanding of the project’s mission,
scope and objectives of the owner and stakeholders. (Generic checklists may not
cover all risks.)
11.3
Risk Management Plan
The risk management plan is
how risk identification, qualitative and quantitative analysis, response
planning, monitoring and control will be structured and performed during the
project life cycle. It may include:
§
Tools to be used
§
Roles and Responsibilities: defines the lead,
support, and risk management membership for each type of action in the risk
management plan
§
Reporting Formats: describes how the results of the
risk management processes will be documented, analyzed and communicated to the
project team, stakeholder and sponsor
- Tracking: documents how all facets of risk
activities will be recorded for the benefit of the current project, future
needs, and lessons learned
11.4 Risk Identification Tools
§
Brainstorming
§
Delphi
Technique – The
same questions are asked individually to different experts, to get an unbiased
opinion
§
Interviewing
§
Strengths, Weaknesses, Opportunities and Threats
(SWOT) Analysis
§
External Risks
- Checklist created from similar projects
11.5 Qualitative
Risk Analysis
Qualitative risk analysis is the process
of assessing the impact and likelihood of identified risks. It prioritizes risks according to
their potential effect on project objectives. The probability and consequences of the risks
are evaluated using established qualitative–analysis methods and tools.
11.6 Quantitative
Risk Analysis
Quantitative risk analysis looks to
quantify the probability of each risk and its consequence on project
objectives.
11.7 Risk Response Planning
Risk response planning is the process of
developing options and determining actions to enhance opportunities and reduce
threats to the project’s objectives.
Mitigation:
Take steps to reduce the probability of
the occurrence and the impact of the risk if it happens. It may take the form
of implementing a new course of action that will reduce the problem (e.g.
conducting engineering tests).
Avoidance:
Eliminate the risk by changing the project
plan.
§
It consists in changing the project plan to
eliminate the risk or to protect the project objective from its impact.
§
Obtaining information
§
Improving communication
§
Reducing scope to avoid high-risk activities
§
Adding resources or time
Transference:
The risk is transferred to another entity.
It will involve the payment of a risk premium and does not actually eliminate
it, but transfers the ownership of it.
§
It consists of seeking to shift the consequence of a
risk to a third party.
§
Transferring the risk gives another party the
responsibility for its management. It
doesn’t eliminate it.
§
It is most effective in dealing with financial risk
exposure.
§
It involves the payment of a risk premium to the
party taking on the risk.
Acceptance:
If the response is acceptance, the team
may develop a contingency plan so if the risk actually happens, there is a way
to mitigate its impact. The impact could be so low (or so high) that no
response is planned ahead of the occurrence.